Re: [allocations-admins] time request for intermetallic
OK, granting. John On Fri, Aug 31, 2012 at 04:24:07PM -0500, Shashi Aithal wrote:
I am fine with it too ...
Shashi ----- Original Message ----- From: "John Valdes" <[email protected]> To: [email protected] Sent: Friday, August 31, 2012 4:15:16 PM Subject: [allocations-admins] time request for intermetallic
Randall Meyer is asking for an additional 50K for his project "intermetallic" for the remainder of the FY. Do we approve? I'm OK with that, fwiw. He originally requested 150K for the 4th qtr but was only given 36K.
https://www.lcrc.anl.gov/jazz/CSAC/project-reports-2012/Individual/intermeta...
John
----- Forwarded message from Randall Meyer <[email protected]> -----
Date: Wed, 29 Aug 2012 09:59:54 -0500 From: Randall Meyer <[email protected]> To: John Valdes <[email protected]> Subject: question
[...] I was also wondering if it were possible to request about 50,000 hours for the month of September since our allocation is currently down to about 2000 hours.
Thanks
randall meyer
----- End forwarded message ----- _______________________________________________ allocations-admins mailing list [email protected] https://lists.lcrc.anl.gov/mailman/listinfo/allocations-admins _______________________________________________ allocations-admins mailing list [email protected] https://lists.lcrc.anl.gov/mailman/listinfo/allocations-admins
participants (1)
-
John Valdes